A can do a work in 15 days and b in 20 days. If they work on alternate days starting with a in how many days will be the work completed

Answers

Answered by sodium30
0

7/120 of work (a+b) Can finished in 1 day

therefore whole work they can finished( if they work alternate day) =120/7

=17 1/7 days