Math, asked by kaushikroysitai03, 12 days ago

A can do a work in 24 days while B can do it in 36 days. They started the work together, after 4 days A left the work but B continues. In how many days the whole work is completed ? 2) 30 days b) 28 days c) 25 days d) 32 days​

Answers

Answered by abhi96255
0

30 days

ping me up if i am correct

Answered by BrainlyHH
3

Answer :-

The whole work is completed in a) 30 days

Explanation :-

A can do a work in 24 days

B can do it in 36 days.

So , by taking LCM of 24 and 36 we get 72

We assume that the total amount of work is 72 units

So , Amount of work done by A is

 =  \frac{72}{24}  = 3 \: units \: /day

Amount of work done by B is

 =  \frac{72}{36}  = 2 \: units/day

A and B together complete 5 units per day

They started together and after 4 days A left the work

So , 5 × 4 = 20 units

Remaining work = 72 -20 = 52 units

Now B alone continues so ,

 =  \frac{52}{2}  = 26 \: days

Therefore total work is completed in 26 + 4 = 30 days.