A can do a work in 40 days. He worked at it for 8 days and then b finished it in 16days. How long will they together take to complete the work?
Answers
Answered by
1
Hi there!
Here's the answer:
•°•°•°•°•°•°<><><<><>><><>°•°•°•°•°•
A can do a work in 40 days
He worked for 8 days
=> Work done by A in 8 days =
Work Remained =
This work is done by B in 16 days
=> No. of days taken by B to do the work
=
•°• A's 1 day work =
& B's 1 day work =
(A+B)'s 1 day work =
•°• If A and B worked together they will take
=
=
•°•°•°•°•°•°<><><<><>><><>°•°•°•°•°•
©#£€®$
:)
Hope it helps
Here's the answer:
•°•°•°•°•°•°<><><<><>><><>°•°•°•°•°•
A can do a work in 40 days
He worked for 8 days
=> Work done by A in 8 days =
Work Remained =
This work is done by B in 16 days
=> No. of days taken by B to do the work
=
•°• A's 1 day work =
& B's 1 day work =
(A+B)'s 1 day work =
•°• If A and B worked together they will take
=
=
•°•°•°•°•°•°<><><<><>><><>°•°•°•°•°•
©#£€®$
:)
Hope it helps