a can do a work in 40 days if a and b can do together in 30 days then the number of days B can complete the work in
Answers
Answered by
2
Answer:
10 days
Step-by-step explanation:
a can do a work in days=40
a and b can do work in days =30
b can do work in days = (40 -30)
= 10 days
Answered by
2
Given :-
- A completes work in 40 days.
- A+B together complete work in 30 days.
Solution :-
Total work = L.C.M of (40,30)
Total work = 120
And :-
==> Efficiency of A = Total work/time
==> Efficiency of A = 120/40
==> Efficiency of A = 3
Similarly :-
==> Efficiency of A+B = 120/30
==> Efficiency of A+B =4
Now :-
==> Efficiency of A = 3
==> Efficiency of A+B = 4
Therefore;
Efficiency of B = 1
==> No. of days taken by B = 120/1
==> No. of days taken by B = 120 days
Hence :-
B will take 120 days to finish the work.
Similar questions