A can do a work in 6 days and b can do it in 8 days . a and b undertook to do it for rs 3200 .with thr help of c they complted the work in 3 days . how much is to be paid to
c.
Answers
Answered by
1
C's 1 day's work =1/3 - ( 1/6 + 1/8)= 1/24
A's wages : B's wages : C's wages = 1/6 : 1/8 : 1/24
= 4:3:1
C's share for 3 days = 3 × 1/24 × 3200= 400
hope it helps, thank you
A's wages : B's wages : C's wages = 1/6 : 1/8 : 1/24
= 4:3:1
C's share for 3 days = 3 × 1/24 × 3200= 400
hope it helps, thank you
Similar questions