A can do a work in 9 days, B can do a work in 7 days, C can do a work in 5 days. A works on the first day, B works on the second day and C on the third day respectively that is they work on alternate days. When will they finish the work ?
Answers
Answered by
3
After day 1, A finishes 1/9 of the work.
After day 2, B finishes 1/7 more of the total work. (1/9) + (1/7) is finished.
After day 3, C finishes 1/5 more of total work. Total finished is 143/315.
So, after day 6, total work finished is 286/315.
Now remaining work = 29 /315
On day 7, A will work again
Work will be completed on day 7 when A is working. He must finish 29/315 of total remaining work.
Since he takes 9 days to finish the total task, he will need 261/315 of the day.
Total days required is 6 + (261/315) days.
Answered by
0
=> After day 1, A finishes 1/9 of the work.
=> After day 2, B finishes 1/7 more of the total work. (1/9) + (1/7) is finished.
=> After day 3, C finishes 1/5 more of total work. Total finished is 143/315.
• So, after day 6, total work finished is 286/315.
=> Now remaining work = 29 /315
• On day 7, A will work again .
=> Work will be completed on day 7 when A is working. He must finish 29/315 of total remaining work.
=> Since he takes 9 days to finish the total task, he will need 261/315 of the day.
• Total days required is 6 + (261/315) days.