A can do piece of work in 15 days b can do in 12 days andc can do it in 8 days if they start work together and a leave 2 days after and b 2 days before completionthen in how many da6s work is finished
Answers
Answered by
0
Total work = 48 unit
efficiency of a+b =4 ————-(1)
efficiency of b+c =3 ————-(2)
According to question
5a +7b +13c = 48
now using 1 and 2 equation
5a+ 7(4-a) +13(a-1) =48
11a =33
a=3 , b =1 , c = 2
Time taken by C = 48/2 =24 days