A can do work 15 days b in 25days and c in 30 days how long will.they take to do the work of they together
Answers
Answered by
0
Answer:
Kai hai khud hi kat le nai marte Puch Puch kar to kare khud hi kat had mana gai tane reply kariye vapas
Answered by
4
Step-by-step explanation:
One Day work of A = 1/15
One Day Work of C = 1/30
One Day work of Both = 1/15 + 1/30
= 2/30 + 1/30
= 3/30
so,
total days = 30/3 = 10 ..days
is your answer mate
Take Care....
Marks As BRAINLIST ...