A can do work in 10 days while B can do the work in 15 days when will they finish the work together
Answers
Answered by
4
For this we have to take the LCM
(10,15) = 30
A= 30÷10 = 3 units a day
B= 30÷15 = 2 units a day
A+B = 5 units a day
So,
15/5 = 3 days
HOPE THIS HELPS
Answered by
0
Consider X work given to A & when B is given with (2/3) of A’s work so they will finish in same time.