A can do work in 24 days A and B acn ro the work in 6 days hwo long will B take to do the work
Answers
Answered by
2
Answer:
A can complete a work in 24 days
or in 1 day, A will do 1/24th work
Similarly B can complete same work in 30 days
and in 1 day, B will do 1/30th work
Given , for 6 days A work alone
so in 6 days A has completed 6* 1/24 work = 1/4th work
work remaining = 1 - 1/4 = 3/4
now A and B work together
so together in 1 day they will complete (1/24 + 1/30)th work
Taking LCM and solving the part we get 120 as LCM so their 1 day work is 9/120th work or 3/40th work
so total work will be completed in 40/3 days
but in 40/3 days, total 1 work will be completed but we need to complete 3/4th work
therefore, (3/4) * (40*3) = 10 days
so total work will be completed in 6 + 10 = 16 days