Math, asked by nishakumari2225, 1 year ago

A can finish 80% of work done
by B in 20% more time taken
by B. working together they can
finish the work to 40 days. In how
many days they will finish the
Work working alone ?​

Answers

Answered by khushichaurasia13
0

Answer:

A will finish the work in 30days

B will finish the work in 10 days