Math, asked by avraamsingh, 4 months ago

A can finish a piece of work in a certain number of days. B takes 45% more number of days to finish the same work independently. They worked together for 58 days and then the remaining work was done by B alone in 29 days. In how many days, could A have completed the work, had he worked alone?​

Answers

Answered by CoruscatingGarçon
14

Answer:

Sambad Kaumudi (Bengali: সংবাদ কৌমুদী) was a Bengali weekly newspaper published from Kolkata in the first half of the 19th century by Ram Mohan Roy. It was a noted pro-Reformist publication that actively campaigned for the abolition(stop) of the Sati Pratha.

Answered by nohlyan5134
8

Answer:

if A=100(20)

than B=145(29)

Efficiency of A= 29

Efficiency of B= 20

than 58 days of boths= 58*49=2842

and b alone work for 29 days = 29*20=580

than total work = 2842+580=3422

A completed the whole work in 3422/29=118 days

Step-by-step explanation: