A can finish a work in 12 days and b can do it in 15 days.after a had worked for 3 days b also joined a to finish the remaing work
Answers
Answered by
3
they work together for 5 days. it means work went last till 5+3= 8days. take a look at picture..
Attachments:
Similar questions