a can finish a work in 15 days and B can do it in 10 days. That worked together for 2 days and then B goes work. In how many days will A finish the remaining work ?
Answers
Answered by
3
A can finish the work in 15 days
1 day = 1/15 of the work
B can finish the work in 10 days
1 day = 1/10 of the work
If they work together
1 day = 1/15 + 1/10 = 1/6 of the work
2 days = 1/6 x 2 = 1/3
Find the work remaining after 2 days:
Work remaining = 1 - 1/3 = 2/3 of the work
Find the days needed for A to finish the remaining work:
Days needed = 2/3 ÷ 1/15 = 10 days
Answer: A will need 10 days to finish the remaining work