A can finish a work in 15 days at 8 hrs a day. You can
finish it in ys at 9 hrs a day. Find in how many
days can we finish it working together 10 hrs a day.
Answers
Answered by
1
Answer:
I take 15*8=120hr and you takes (20/3)*9=60hr to complete the work respectively ,overall time taken to complete the work togather=(120*60)/180=40hr
let x days are required to complete the work togather working 10hr a day then
10*x=40
x=4days
5 years agoHelpfull: Yes(1) No(0)