Math, asked by deep41913, 9 months ago

A can finish a work in 18 days and B can do the same in 15 days. B worked for 10days and left the job. In how many days, A alone can finish the remaining work.​

Answers

Answered by TaruYadav
0

Answer:

12 min from the range of the kids save it smoove

Answered by rideranshusingh
3

LCM of 18,15,10 is 90

Then 90/18 = 5 days