A can finish a work in 18 days and B can do the same work in ⅓ rd of the time taken by A. Then, working together, what part of the same work they can finish in a day?
Answers
Answered by
0
what is this answer
Answered by
0
Answer:
Step-by-step explanation:
B do the work in 18/3 = 6 days
A do the work in one day is 1/18
B do the work in one day is 1/6
Together do the work in 1/6 + 1/18 = 2/9