A can finish a work in 24 days, B in 9 days, and C in 12 days. B and C started the work but are forced to leave after 3 days. In how many days is the remaining work done by A. please explain dont give direct answer​

Answers

Answered by realchi2007
1

Answer:B+C)'s 1 day's work =(  

9

1

+  

12

1

)=  

36

7

 

Work done by B and C in 3 days =(  

36

7

×3)=  

12

7

 

Remaining work =(1−  

12

7

)=  

12

5

 

Now,  

24

1

 work is done by A in 1 day.

So,  

12

5

 work done by A in (24×  

12

5

)=10 days.