A can finish the work in 16 days while B can finish the work in 8 days. After A started the
work alone, B joined him after 4 days. Find out the total Time taken to finish the work
Answers
Answered by
3
Answer:
8 days
Step-by-step explanation:
A can finish the work in 16 days
B can finish the work in 8 days.
total work a will do in one day = 1/16
total work a will do in 4 day = 1/16*4 = 1/4
remaining work = 1- 1/4 = 3/4
total work b can do in one day = 1/8
they both worked = 1/16+1/8 = 3 /16
total time taken to do the remaining work = 3/4 / 3/16
3/4 * 16/3
4 days
adding all days = 4+4 = 8 days
Answered by
0
Step-by-step explanation:
8 days as half of 16 is 8 and is also a divisable by 4