Math, asked by shyamligupta6548, 1 year ago

A can finish work in 18 days b can do in 15 days.B worked for 10 days and left the job how many daysa alone finish the job

Answers

Answered by raj981
3

Step-by-step explanation:

work \: done \:  by \: a \: in \: 1 \: day \:  =  \frac{1}{18}  \\ work \: done \:  by \: b \: in \: 1 \: day \: =  \frac{1}{15}  \\ work \: done \:  by \: b \: in \: 10 \: days \: =  \frac{1}{15}  \times 10 =  \frac{2}{3}

work \: left \:   = 1 -  \frac{2}{3} =  \frac{1}{3}   \\ days =  \frac{ \frac{1}{3} }{ \frac{1}{18} }  \\ days \:  =  \frac{18}{3}  = 6

hope it helps you

please mark as brainliest