A can have a piece of work done in 8 days, B can work three times faster than the A, C can work five times faster than A. How many days will they take to do the work together ?

(a) 3 days (b) 8/9 days (c) 4 days (d) can't say

Answers

Answered by prakshali63
0

they will do in 3 days

Answered by nerdygamer5
0

they will do together in 3 days