Math, asked by GangotriHalder, 1 year ago

A certain number of men can finish a work in 50 days. If there are 7 more men, the work can be completed 10 days earlier. How many men were originally there?

Answers

Answered by Shrutdevi
3

Answer: 35 men


Step-by-step explanation:

Let ' x ' be the number of men :


x men = 50 days

x + 7 men = 40 days


On cross multiplying :


40x = 50x + 350

50x - 40x = 350

10x = 350

x = 350 / 10

x = 35 men


Therefore, originally there were 35 men...




GangotriHalder: Sorry...You might have made a mistake...The correct answer is 28..
Similar questions