A complete a work in 20 days while B is 25 percentage more efficient than A.B works for 6 day and and left the remaining work is completed by C in 15 days .Find in how many days C can complete a whole work alone.
Answers
Answered by
5
Answer:
Efficiency of A = 100
Efficiency of B = 125
= 4:5
Therefore Ratio of time taken is 5:4
Here 5 corresponds to 20 days so 4 will equals 16 days.
Total work will be 80
B alone completed 30 work in 6 days.
So remaining work is 50.
Therefore efficiency of c can be found out. Which equals 10/3.
So time taken by C equals
80*(3/10)
= 24 days
PLZ MARK AS BRIANLIEST,FLW ME AND THX FOR THE SUPERB QUESTION