Math, asked by edhanad7eepKkh, 1 year ago

A completes 80% of a work in 20 days. then b also joins and a and b together finish the remaining work in 3 days. how long does it need for b if he alone completes the work?

Answers

Answered by sreeramesan123
0
i am not sure but i feel its 22 days

Answered by rahulkannan356
0
a completes 80/100 in 20 days 
(a+b) completes 20/100 in 3 days 
 

a completes 80/100/20 of the work in 1 day 
=>4/100 in a day 
in 3 days a finishes 12/100 
so b has to  finish 8/100 in 3days 
=>b finishes 8/300 of the work in 1 day 
=>it takes 1/8/300 =300/8 days to finish the work