A completes work in 8 days ,B completes the same work in 4 days , if they started working together then in how many days they will complete work ?
Answers
Answered by
0
Answer:
8/3 days
Step-by-step explanation:
Total work can be represented as 1.
Let, n be the no. of days.
FOR A
days taken = 8
work done by A in one day = 1/8
FOR B
days taken = 4
work done by A in one day = 1/4
∴n x (work done by A in one day + work done by B in one day) = 1
n (1/8 + 1/4) = 1
n (3/8) = 1
n = 8/3
therefore, 2.667 or 8/3 days.