Math, asked by kalpanasinghsingh8, 5 months ago

A construction project has to be completed by
5 workers in 24 days. Suddenly the company
decides to complete the project fast by hiring
extra workers. How many workers are needed to
complete the construction project in 15 days?​

Answers

Answered by Nidhisinghbhb
7

Answer:

Number of workers | Number of days

5 workers. | 24 days

x workers. | 15 days

5 × 15 = 24×x

24 x = 15×5

x = 15 × 5/ 24 = 25/8

Answered by goluk428434
0

Answer:

Step-by-step explanation:

Similar questions