Math, asked by ishavkhatwani4726, 1 year ago

A contract is to be completed in 46 days and 117 men were set to work, each working 8 hours a day. After 33 days, 4/7 of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?

Answers

Answered by shadowhacking08
2

Answer:

Step-by-step explanation:

A contract is to be completed in 46 days and 117 men were set to work, each working 8 hours a day.

After 33 days 4/7 of the work is completed.

Find how many man-hrs expended to complete 4/7 of the job?

117*8*33 = 30888 man-hrs

let t = total man-hrs required for the job

4%2F7t = 30888

t = 54054 man hrs

:

How many additional men may be employed so that the work be completed in time, each man now working 9 hours a day?  

The remaining 3/7 of the work required: 3%2F7*54054 = 23166 man-hrs

let m = no. men working 9 hrs a day to finish the job in 13 days (46-33)

 

m*9*13 = 23166

117m = 23166

m = 198 men total

then

198-117 = 81 more men required

:

:

See of that adds up

117*8*33 = 30888 man-hrs for the first 33 days

198*9*13 = 23166 man-hrs for the last 13 days

---------------------

total man-hrs: 54054 man-hrs  


shadowhacking08: mar me breainliest]
abhineet15: nice explanation!!
abhineet15: sis♥
Similar questions