A contract is to be completed in 56 days and 104 men were set to work, each working 8 hours a day. After 30 days, 2/5 of the work is finished. How many additional men may be employed so that work may be completed on time
Answers
Answered by
0
Answer:
Step-by-step explanation:
199
Similar questions
History,
6 months ago
English,
6 months ago
Math,
6 months ago
Biology,
1 year ago
Social Sciences,
1 year ago