A contract is to be completed in 56 days and 104 men were set to work, each working 8 hours a day. After 30 days, 2/5 of the work is finished. How many additional men may be employed so that work may be completed on time

Answers

Answered by Anuradha1haddi
0

Answer:

Step-by-step explanation:

199