Math, asked by pinkalcusmc, 5 months ago

A contract on construction job specifies a
penalty for delay of completion beyond a
certain date as follows:200 for the first
day, 250 for the second day, 300 for
the third day, etc., the penalty for each
succeeding day being 50 more than for
the preceding day. How much money the
contractor has to pay as penalty, if he has
delayed the work by 30 days ?​

Answers

Answered by priyankmaharshi06
1

Answer:

Answer is 27750 (correct answer)