a contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs 200 for the first day, Rs 250 for the second day, Rs 300 for the third day,etc.. the penalty for each succeeding day being Rs 50 more than for the preceeding day. how much money the contractor has to pay as penalty, if he has delayed the work by 30 days?

Answers

Answered by MaheswariS
24

\underline{\textsf{Given:}}

\textsf{Penalty for the 1 st day=Rs.200}

\textsf{Penalty for the 2 nd day=Rs.250}

\textsf{Penalty for the 3 rd day=Rs.300 and so on}

\underline{\textsf{To find:}}

\textsf{How much money the contractor has to pay as penalty}

\textsf{if he has delayed the work by 30 days}

\underline{\textsf{Solution:}}

\textsf{Penalty for the successive days are}

\mathsf{200,250,300,.............}

\textsf{Clearly this is an A.P with a=200 and d=50}

\underline{\textsf{Penalty has to pay for 30 days}}

\boxed{\mathsf{S_n=\dfrac{n}{2}[2a+(n-1)d]}}

\mathsf{S_{30}=\dfrac{30}{2}[2(200)+(30-1)50]}

\mathsf{S_{30}=15[400+1450]}

\mathsf{S_{30}=15{\times}1850}

\mathsf{S_{30}=27750}

\underline{\textsf{Answer:}}

\textsf{Total penalty has to pay = Rs.27750}

\underline{\textsf{Find more:}}

In an ap if s3=24 and s4=30 then find a4 ...

please friends solve it fast it's urgent please friends ...​

https://brainly.in/question/18360783

Find the sum of all natural numbers between 200 and 1000 exactly divisible by 6.Ans. S = 79800​

https://brainly.in/question/23303022

If the sum of the first n terms of A.P. 30,27,24,21,...... is 120, find the number of terms and the last term.​

https://brainly.in/question/12113379

Answered by cutegirl1417
5

Answer:

answr

search

What would you like to ask?

MATHS

avatar

Asked on October 15, 2019 by

Gurvinder Naruka

A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs. 200 for the first day, Rs. 250 for the second day, Rs. 300 for the third day, etc., the penalty for each succeeding day being Rs. 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days.

Video Explanation

Solution To question ID 466119

ANSWER

It can be observed that these penalties are in an A.P. having first term as 200 and common difference as 50.

a=200,d=50

Sum upto n terms (S

n

)=

2

n

[2a+(n−1)d]

Penalty that has to be paid if he has delayed the work by 30 days

=S

30

= S

30

=

2

30

[2(200)+(30−1)50]

=15[400+1450]

=15(1850)

=27750

Therefore, the contractor has to pay Rs 27750 as penalty.

Answer verified by Toppr

329 Views

Was this answer helpful?

answr

Get Instant Solutions, 24x7

No Signup required

girl

Practice important Questions

NCERT Solutions for Class 10 Maths Chapter 5

49 Qs

R.D. Sharma Solutions for Class 10 Maths Chapter 9

91 Qs

Related Questions to study

Certain numbers appear in both the arithmetic progressions 17,21,25.......and 16,21,26 ..... then the sum of the first two hundred terms appearing in both is

Study later

View solution

Find the eleventh term from the last term of the A.P :

27, 23, 19,.....,-65.

Similar questions