Math, asked by gowrikar123, 3 months ago

a contract on construction jobs specifies a penalty for delay of completion beyond a certain date as follows rupees 200 for the first day 20 250 for second day rupees 300 for the third day etx . 1) how much money the contractor has to pay has penalty if he has delayed the work by 10 days? 2) which mathematical concept is used in the above problem? 3) which value should be promoted in this problem? ​

Answers

Answered by suraj22bbk
0

Answer:

650

Step-by-step explanation:

10th position in AP =a+(n-1) d

Similar questions