Math, asked by Shashishekar2576, 11 months ago

A contractor agreeing to finish a work in 150 days employed 75 men each working 8 hours daily in 90 days only 2/7 of the work was completed

Answers

Answered by rishika79
0

Answer:

Step-by-step explanation:

He need total 225 workers work 10 hours daily for 60 days to complete the work.(The total working hours they already worked s 54000 hours. that is 2/7. so 1/7 will b 27000hrs. multiply it with 5 .then it wil b 135000. That means the remaining work. Then divide it with the remaining days and hours going to work. That is 60*10 =600. so 135000/600 =225 workers. 225-75 =150 more workers needed

Hope it helps you....

Answered by gujjarankit
0

Answer:

question is incomplete as it is not given that whether they have to complete it within time

Step-by-step explanation:

my answer is as according if they have complete it on time...281(75+206) 206 more will be employed to complete the work on time

....even after this kindly recheck your question as it is incomplete