Math, asked by surendranathchowdary, 9 months ago

A contractor decided to build a farmouse in 60 days. He employed 150 men in the beginning and 130 more after
40 days and completed the construction in stripulated time. If he had not employed the additional men, how many
days behind the schedule would it have been finished?
Ans. 13 days.​

Answers

Answered by inmatn
1

Answer:

17.333 Days

Step-by-step explanation:

280 Persons x 20 Days = 5600

Divided by 150 persons = 37.333 Days

37.333 - 20 = 17.333 Days