A contractor employed 180 men to build a house in 50 days. After 8 days, he was joined by 36 more men. In how many days will the remaining work be finished?
Answers
Answered by
0
Answer:
42 days ( aprox)
Step-by-step explanation:
t=50×180÷(180+36)=50×180÷216=42 days (aprox)