A contractor employed 180 men to build a house in 50 days. After 8 days, he was joined by 36 more men. In how many days will the remaining work be finished?​

Answers

Answered by srijannaiya
0

Answer:

42 days ( aprox)

Step-by-step explanation:

t=50×180÷(180+36)=50×180÷216=42 days (aprox)