a contractor employed 210 men to be built a stadium in 60 days if after 12 days 70 additional men joined the work in how many days would the work finish
Answers
Question:-
A contractor employed 210 men to be built a stadium in 60 days if after 12 days 70 additional men joined the work in how many days would the work finish.
Solution:-
a) A contractor employed 210 men to be built a stadium in 60 days.
b) After 12 days 70 additional men joined.
{ According to ( a ) & ( b ) }
Reamaining days of work of 210 employee after 12 day :-
--› 60 days - 12 days = 48 days
--› 210 men's = finish their work in 48 days
{ From ( a ) & ( b ) }
We know 70 additional men joined to 210 men to built stadium.
--› 280 men's = let finish their work in x day's
Now, To find day's ( x ) for finishing their work we take product of 280 men's and 48 day's with respect to 280 men's
Hence they need 36 day's to finish their work.
Answer:
36 fays is answer
ok thanks