Math, asked by chauhansrb6498, 11 months ago

A contractor employed 210 men to build a house in 60 days. After 12 days,he was joined by 70 more men. In how many days will the remaining work be finished

Answers

Answered by SidhantVerma77
4

Answer:

280 men can build the house in 45 days.

Step-by-step explanation:

210 men can build a house in 60 days

1 Man can build the house in 60×210 days

By condition,

He was joined by 70 more men. Therefore, total men is 210+70=280 men.

280 men can build the house in 60×210/280

= 60×21/28

= 60×3/4

= 15×3 = 45(ans)