Math, asked by MechAlpha, 3 months ago

A contractor employed 210 workers to unload goods from a ship in 18 days. After 4 days it was found that only 1/6 part of the work was done. How many more men had to be employed to finish the work in time?

Answers

Answered by Priyanshulohani
0

Answer:

Given that,

Let the total work to be done =1

210 men build a house in 60 days

each man 1 day work =

210×60

1

After 12 days,

Total work done by 210 workers in 12 days

=

210×60

1

×210×12=

5

1

70 extra workers joined the work now

total workers =280

Remaining work =1−

5

1

=

5

4

.............(1)

Let the remaining work finished in next X days

Total work done by 280 workers in X days =

210×60

1

×280×X ..................(2)

Equation (1)=(2)

5

4

=

210×60

1

×280×X

X=36 Days