Math, asked by mmdboloz50431, 1 year ago

A contractor employed 30 men to do a piece of work in 38 days . after 25 days he employed 5 men more nd the work was finished one day earlier . how many days he would have been behind , if he had not employed additional mean

Answers

Answered by abhinandan1431
1
38 days.. bz in first line u hav written that... contractor employed 30 men to comple a work in 38 days...
Answered by Anonymous
3
Hey mate!

Here's your answer!!
_________________________

There's even an easy method.

We know that,

Earlier, 30 men did a piece of work in 38 days.

After 25 days, (30 + 5) = 35 men can do the work in 12 days.

So, 35 men fan finish the remaining work in 12 days.

∴ 30 men can do it in...

 \frac{12 \times 35}{30}  = 14

Hence, 30 men can do a piece of work in 14 days, that is, the contractor would be one day behind.
_________________________
Hope it helps you!!

✌ ✌ ✌

✪ Be Brainly ✪