Math, asked by ajay100036, 11 months ago

a contractor employed 560 men to complete a project in 7 months If he wishes to complete the same project in 5 months, how many more men should he employ

Answers

Answered by madhav1767
2

Answer:

560/7:x/5

560x5/7=x

2800/7=x

400=x

400 employees wanted more