Math, asked by kansh421, 9 months ago

A contractor employed 63 workers to complete a piece of work in 9 days. After working for 2 days, the contractor is told to complete the work in 3 days. How many more workers must be employed to complete the work?​

Answers

Answered by kushagrh9191
2

this is not very easy

Similar questions