Math, asked by lbsingh8874088411, 1 month ago

a contractor employed 800 man to complete a project of construction a bridge in 5 months if he wishes to complete the project in 4 months how how many more man should he employ​

Answers

Answered by swarup2k7
0

Answer:

160 more man.

will be the answer.