a contractor employes 360 men who can finish a certain piece of work in 11 months. how many more men must be employed to complete the job in 9 months?​​

Answers

Answered by dinesh34304
4

Answer:

a contractor employes 360 men who can finish a certain piece of work in 11 months. how many more men must be employed to complete the job in 9 months?

Answered by xxxlegendxxx
1

Answer:

answer =44men more

Step-by-step explanation: