A contractor estimates that 3 persons could rewire Jasminder's house in 4 days. If,
he uses 4 persons instead of three, how long should they take to complete the job?​


Anonymous: hehehe
Anonymous: answer chahiye tha to bata dete bro
KritarthGPathak: nhi aap bata di to or pareshan kyu karta aapko
Anonymous: accha ji
KritarthGPathak: haa
KritarthGPathak: lekin aap mujhe unfollow kyu kar di

Answers

Answered by Anonymous
6

Answer:

According to the estimation in rewiring Jasminder's house

Number of persons required =3

Number of days required =4

So, to rewire a house by 1 person it will take 4×3=12 days

And to do job by 4 persons, days required =

12/4

=3 days