Math, asked by AyushDevli02, 11 months ago

A contractor estimates that 3 persons could rewire Jaswinder's House in 4 days. If ,
he uses 4 persons instead of three, how should they take to complete the job?

Answers

Answered by arnavcube123456789
5

Answer:

16/3 days

Step-by-step explanation:

If 3 men for 4 days

then 4 men for how many?

Cross multiply and get answer

Similar questions