Math, asked by deepakjaiswar2305199, 10 months ago

a contractor has 420 man to finish a piece of work in 9 month how many extra man will be require to finish the work in 6 month?

Answers

Answered by avinashkr19
0
required man to finish work = 630 Man

in 9 month 420 man is required
So in 1 month 420×9 man is required
again in 6 month 3780÷6=630 man is required

deepakjaiswar2305199: solve it
avinashkr19: ok
Similar questions