Math, asked by rahulrks2331, 6 months ago

A contractor has the target of completing a work in 40 days .he employed 20 person who completed 1/4 of the work in 10 days and left . the number of persons he has to employs finish the remaining part as per target it.​

Answers

Answered by puzzlepedia
2

Answer:

Answer : 20employs for 30days

Step-by-step explanation:

PUZZLE PEDIA  -------  YOUTUBE CHANNEL

Thanks for spending time with Puzzle Pedia! ♥♥

HOPE THIS WILL HELP YOU...

Attachments:
Answered by vinitatater1602
0

Step-by-step explanation:

Answer : 20 employs for 30 days