. A contractor takes a contract to construct
bridge in 6 months and employed 120 men
Due to some emergency, he was asked to
complete the job in 4 months. How many
more men should he put in for the job?
Answers
Answered by
4
Answer:
80men
Step-by-step explanation:
6months=120men
4 months =?
cross multiplication, 4 X 120 = 4 X 20= 80
6
Answered by
6
Answer:
180
Step-by-step explanation:
Inverse proportion method:
If 120 people can do a job in 6 months then
how many people cn altogether do the job in 4 months
(No of people to complete the job in 6 months)x(Total time)
=(No of people to complete the job in 4 months)x( Total time)
let the number of to complete the job in 4 months be 'a'
120 x 6 = 4a
a= (120 x 6)÷4
so a = 180
finally the number of people to complete the job in 4 months are 180
Extra knowledge : The person will have to hire
(180 - 120= 60) people to complete the work in 4 months
Similar questions