a contractor undertakes to build a wall 1000m long in 50 days . he employs 56 men but at the end of 27 days he finds that only 448 m of wall is built . how many extra men the contractor must employ so that the work is completed in time ? plz answer asap
Maham1:
is the answer 125 ?
Answers
Answered by
0
he needed to take 25workers more