A contractor undertakes to dig a canal.6 km long,in 35 days and employed 90 men.He finds that after 20 days only 2km of canal have been completed.How many more men must be employed to finish the work in time?

Answers

Answered by leninviki
8
M1*D1*W2=M2*D2*W1
90*20*4=M2*15*2
6*10*4=M2
M2=240
240-90=150
required men 150