A contractor undertakes to do a piece of work in 36 days and employs 15 men to work 9 hours a day. But after 24 days, he finds that only 3/5 of the work is done. He then employs 3 more men. For how many hours a day should all the men work together to finish the work on time?
Answers
Answer:
To finish the work, 18 men has to work for 10 hours a day.
Step-by-step explanation:
Given the number of days = 36
Number of men working = 15
Number of days worked = 24
Number of working hours per day = 9
Completed work = 3/5
Number of working hours in 24 days is
15 men have done 3/5 work in 216 hours
15 men can do the whole work in
1 man can do the whole work in 360 x 15 = 5400 hours
Remained work is
1 man can do 2/5 of the work in
Given 3 more men have deployed to do the work.
Total men are 15 + 3 = 18
To complete the work each man has to work,
Days left = 36 – 24 = 12 days
Men required to complete the work in 12 days
So, number of hours to work a day is
Therefore, to finish the work, 18 men has to work for 10 hours a day.
For more problems
https://brainly.in/question/1892864
https://brainly.in/question/37382213